The work—carried out by teams from the Power Plant Maintenance Company, the Industrial Construction Enterprise No. 9, and the plant’s own personnel, among others—covers the boiler, the condenser, and the two regenerative air preheaters, the facility’s acting director, Victor Hugo Gonzalez, told Prensa Latina.
One of the most complex tasks is the comprehensive cleaning of the boiler, which has been in continuous operation for 14 months without such a procedure; this will require approximately 15 days of sustained work by the crews.
The program also includes cleaning the condenser and replacing the baskets in both regenerative air preheaters—a phase considered a “critical path” due to the extensive dismantling and replacement work involved.
According to Gonzalez, the plan includes addressing 160 pending technical issues previously identified by inspectors and operators, which will allow for the resolution of accumulated defects and an assessment of the equipment’s condition.
Unit 1 at Felton, which has a capacity of 260 megawatts, has been operating at only about 110 megawatts in recent weeks, underscoring the necessity of these repairs for the national power grid.
Adhering to the schedule will require close coordination among the participating entities, given the complexity of the tasks and the need to complete the work within the established timeframe.